2023-2026 HTMPO TIP
Record of Adoption and Changes
- September 22, 2022: TIP adopted by HTMPO Policy Committee
- October 4, 2022: Administrative modification to address comments on the draft by the FHWA.
- January 26, 2023: Amended by the adjust the scope of Pedestrian Improvements: LA 1, Audubon Ave. Bowie Roadto include an additional intersection.
- February 6, 2023: Administrative modification to project H.013453 BAYOU BLUE (LA 316) SIDEWALKS increasing the engineering phase from to $173,280.
- May 4, 2023: Amended to include the project H.013116 LA 20 Widen: LA 307 – S. Vacherie: Environmental Phase at $225K HSIPPEN at 100% in FFY 2023; Construction Phase of $17.1M in HSIPPEN at 90/10% in FFY 2023.
- May 12, 2023: Administrative modification to make technical corrections in the document and H.013116 LA 20 WIDEN: LA 307 – S. VACHERIE change Environmental Phase from $225k in HSIPPEN at 100% in FFY 2023 to $1M in HSIPPEN at 100% in FFY 2023.
- July 27, 2023: Administrative modification to H.015654 CITY OF THIBODAUX PED IMPROVEMENTS: LA 1, BOWIE ROAD, AUDUBON AVENUE change construction phase from FFY 23 to FFY 26. Administrative modification to H.013714 VALHI BOULEVARD SHARED-USE PATH (HOUMA) to change construction phase from $350k in HSIPPEN at 100% and $63,492.40 in STP50-200k at 80/20 in FFY 2024 to $350k in HSIPPEN at 100% and $63,492.40 in STP50-200k at 80/20 in FFY 2025. Amendment to H.014802 LA316 & LA 24: MILL,OVRLY,GRADE RAISING,HFST to add construction phase $3.58M in STGEN, $1.535M in HSIPPEN at 100% and $600k in PROTECT at 80/20 in FFY 2024. Amendment to H.014849 US 90: 0.9 MI W LA 311 – MCMAHON CANAL to add construction phase $17.5M in NHPP at 80/20 and $xx in DEMO in FFY 2023. Administrative Modification to H.014849 US 90: 0.9 MI W LA 311 – MCMAHON CANAL to include $3,400,000 in DEMO in FFY 2023.
- August 2, 2023: Administrative Modification: Lafourche Council on Aging recieved FTA Enhanced Mobility for Seniors and Individuals with Disabilities funding to purchase (2) 12 passenger vehicles totaling $280,852.00 (85% federal share of $238,724.20; 13.8% local match of $38,757.58; 1.2% Parish Transportation funds of $3,370.22).
- September 15, 2023: Administrative modification to H.013269 AUDUBON AVE OVLY: LA 1 TO TERREBONNE P/L to increase the Construction phase from $469,380 in STP50-200k at 80/20 in FFY 2024 to $1.2M in STP50-200k at 80/20 in FFY 2024. Administrative modfication to H.013340 VALHI BLVD, MULTI-USE TRAIL, PHASE 1 to decrease construction phase from $973,020 in STP50-200k at 80/20 in FFY 2024 to $890k in STP50-200k at 80/20 in FFY 2024.
- October 26, 2023: Amended to remove the following projects from HTMPO ‘s 2023-2026 TIP: H.013402 LA1 & LA308 PED & MULTIUSE PATH (LOCKPORT), H.013404 LA 1 SIDEWALKS (CUT-OFF), and H.013490 CENTRAL LAFOURCHE MULTI-USE PATH PH 1A. Amendment to H.013714 VALHI BLVD SHARED-USE PATH (HOUMA) to add Engineering phase $139k in HSIPPEN at 100% in FFY 2024. Amendment to include H.015662 VALENTINE PONTOON BRIDGE (HBI) add Environmental phase $62.5k in LOCAL in FFY 2024; add Engineering phase $693.5 in LOCAL in FFY 2024; add Construction phase $3.3M in EARMARK at 80/20, $1.2M in FBROFF at 80/20 and $1.6M in LOCAL in FFY 2025. Amended H.972506.1 (HTMPO TRANS PLAN UPDATE SFYS 2024-2025) to add $275,000 STP50-200K funding at 80/20 in FFY 2024.
- November 16, 2023: Administrative modification to H.015662 VALENTINE PONTOON BRIDGE (HBI) to move Environmental phase $62.5k in LOCAL and Engineering phase $693.5 in LOCAL from FFY 2024 to FFY 2023.
- December 15, 2023: Administrative Modification to Canal Boulevard Overlay: Jackson Street to LA 1 to move $145,560 STP50-200k from FFY 2023 to FFY 2024.
- January 25, 2024: Amended H.013403 LA 20 & LA 304 SIDEWALK IMP (CHACKBAY): Remove Engineering phase $40k in STP50-<200k at 80/20 in FFY 2023 remove Construction phase $262,710 in STP50-<200k at 80/20 in FFY 2024.
- April 25, 2024: Amended H.012859 CIVIC CENTER BLVD @ VALHI BLVD to add Engineering phase $375,757 in STP>200k at 80/20 in FFY 2024.
- May 16, 2024: Administrative Modification to H.013453 BAYOU BLUE (LA 316) SIDEWALKS moving ROW phase to FFY25; H.012859 CIVIC CENTER BLVD @ VALHI BLVD moving ROW phase to FFY25; and H.013940 LA 648 & ACADIA ROAD INTERSECTION IMPROV moving ROW phase to FFY25.
- July 2, 2024: H.013429 DOWNTOWN THIBODAUX SIDEWALKS Administrative modification to change construction phase from $1M in STP50-200k at 80/20 in FFY2024 to $1.245M in STP50-200k at 80/20 in FFY2024
- July 24, 2024: Administrative Modifications to the following:
- H.013453 BAYOU BLUE (LA 316) SIDEWALKS – Move ROW phase to FFY25.
- H.012859 CIVIC CENTER BLVD @ VALHI BLVD – Move ROW phase to FFY25.
- H.013940 LA 648 & ACADIA ROAD INTERSECTION IMPROV.- Move ROW phase to FFY25.
- H.013429 DOWNTOWN THIBODAUX SIDEWALKS – Change construction phase from $193,200 in STP50-200k at 80/20 in FFY2024 to $1M in STP50-200k at 80/20 in FFY2024.
- H.013116 LA 20 Widen: LA 307 – S. Vacherie: Administrative modification to include CE & IDC in total construction costs. Total construction costs will increase from $18,810,000 to $19,810,000 in FFY 2023.
- H.014849 US 90: 0.9 MI W LA 311 – MCMAHON CANAL (Lafourche and Terrebonne): Administrative modification to include CE & IDC in total construction costs. Total construction costs will increase from $14,100,000 to $15,510,000 in NHPP in FFY 2023; and $3,400,000 to $3,740,000 in DEMO in FFY 2023.
- H.015662 VALENTINE PONTOON BRIDGE (HBI): Administrative modification to include CE & IDC in total construction costs. Total construction costs will increase from $3,300,000 to $3,630,000 in EARMARK in FFY 2025; increase from $1,200,000.00 to $1,320,000 in FBROFF in FFY 2025; and increase from $1,600,000.00 to $1,760,000.00 in LOCAL in FFY 2025.
- H.002244 LA 56: Boudreaux Canal MB Replacement: Administrative modification to include CE & IDC in total construction costs. Total construction costs will increase from $23,703,690 to $26,074,059 in STPFLEX in FFY 2023.
- H.972506.1 (HTMPO TRANS PLAN UPDATE SFYS 2024-2025): Administrative modification to project phase description. Modify “Construction” to “Planning”.
- H.013269 AUDUBON AVE OVLY: LA 1 TO TERREBONNE P/L: Change Phase 6 (Construction) from $1.2M STP 50 – 200K at 80/20 in FFY 2024 to $1.51M STP 20-200K at 80/20 in FFY 2024.
- H.015654 CITY OF THIBODAUX PED IMPROVEMENTS: LA 1 at Bowie Road/ LA 1 at Audubon Ave.: Change Phase 5 (Design) from $20K in Local in FFY 2023 to $20K in STP 50 – 200K at 80/20 in FFY 2025. Modify name to match STIP: CITY OF THIBODAUX PED IMPROVEMENTS.
- September 18, 2024: Administrative modifications to H.012859: Civic Center Boulevard at Valhi Blvd.to increase Phase 5 from $375,757 in STP>200k at 80/20 in FFY 2024 to $376,000 in STP50-200K at 80/20 in FFY 2024 and modification to Phase 3 from 150k STP<200k @80/20 FFY23 to 150K STP50 – 200k@ 80/20 for FFY 2025.
- October 24, 2024: H.011972: LA 3040: ICW HOUMA TUNNEL REHABILITATION: Amendment to remove Phase 6 (Construction) $15M in NHPP at 80/20 in FFY 2024.
- November 15, 2024: Administrative modification to the following projects:
- H.011973 LA 315: ICWW MB REHAB (DULARGE) Decrease Engineering phase from $1,800,000 to $705,000.
- H.011962 LA 1: CO CANAL MB REHAB (LOCKPORT)(HBI) Decrease Engineering phase from $1,800,000 to $525,000.
- H.011986 LA 58: B TERREBONNE MB RH(MONTEGUT)(HBI) Decrease Engineering phase from $1,200,000 to $650,000.
- H.013818 LA 308: B LAFOUR MB RH(GOLDEN MEADOW)(HBI) Decrease Engineering phase is from $1,200,000 to $650,000.
- November 19, 2024: Administrative modification to H.011962 LA 1: CO CANAL MB REHAB (LOCKPORT)(HBI): Move Engineering phase at $525,000 from 2024 to 2025. Administrative modification to H.013818 LA 308: B LAFOUR MB RH(GOLDEN MEADOW)(HBI): Move Engineering phase at $650,000 from 2023 to 2025.
February 13, 2025: Amended H.002244 LA 56 : Boudreaux Canal MB Replacement to add Right-of-Way Phase at $2.368 million in STPFLEX at 80/20 in FFY 2025. Also changed the Construction Phase from $23,703,690 in FFY 2023 to $23.7 million in FFY 2026. Other amendments included the addition of two new projects:
H.015616 Lafourche Bayou Bridge (HBI): Feasibility Study at $75,000 FHWA BIP at 80/20 in FFY 2026. City of Thibodaux Asphalt overlay for Glenwild Drive (St. Patrick to Canal), St. Patrick Street, and Plantation Road (in City limits): Engineering/Design: $574,000 STP50K-200K at 80/20 in FFY 2026; Construction: $1,875,242.50 STP50K-200K at 80/20 in FFY 2027 & Contingency: $187,524.25 STP50K-200K at 80/20 in FFY 2027.
February 28, 2025: Administrative Modification to add project numbers for various previously approved projects; H.013714 change project name from “Valhi Boulevard Shared-Use Path” to “VALHI BLVD SHARED-USE PATH (HOUMA)” and change construction phase from $63,492.40 in STP50-200K at 80/20 and $350K in HSIPPEN at 100% in FFY 2025 to $713K in STP50-200K at 80/20 and $350K in HSIPPEN at 100% in FFY 2025.
March 12, 2025: Administrative Modification updating the name for H.015654 CITY OF THIBODAUX PED IMPROVEMENTS and changing design phase from $20K in STP50-200K at 100% in FFY 2025 to $20K in STP50-200K at 80/20 in FFY 2025.
April 15, 2025: Administrative Modification to H.013714 VALHI BLVD SHARED-USE PATH (HOUMA):Change construction phase $713K in STP50-200K at 80/20 and $350K in HSIPPEN at 100% in FFY 2025 to $1.1M of HSIP-VRU at 90/10 in FFY 2025.
April 24, 2025: Amended the following projects:
- H.002244 LA 56 BOUDREAUX CANAL MB REPLACEMENT: Add utility relocation phase of $33K in STPFLEX at 80/20 FFY 2025. Change construction phase from $23.7M in STPFLEX at 80/20 in FF 2026 to $44M in STPFLEX at 80/20 in FF 2026.
- H.014802 LA316 & LA 24: MILL, OVRLY, GRADE RAISING, HFST: Change construction phase from $3.58M in STGEN in FFY 2024 to $4.41M in STGEN in FFY 2025. Change construction phase from $1.535M in HSIPPEN at 100% in FFY 2024 to $5.7M in HSIPPEN at 100% in FFY 2025. Change construction phase from $600K in PROTECT at 80/20 in FFY 2024 to $268K in PROTECT at 80/20 in FFY 2025. Add construction of $1.8M in STPFLEX at 80/20 in FFY 2025.
- H.015654 CITY OF THIBODAUX PED IMPROVEMENTS: Renames project. Change design phase from $20K in STP50-200K at 100% in FFY 2025 to $20K in STP50-200K at 80/20 in FFY 2025.
- H.016383 LAFOURCHE SCHOOL ZONES CROSSING UPGRADES: New Project. Add design phase of $100K in STP50-200K at 80/20 in FFY 2025. Add construction phase of $135K in STP50-200K at 80/20 in FFY 2026.
- H.016386 LA 311 SAVANNE INTERSECTION IMPROVEMENTS: New Project. Add environmental phase of $50K in STP50-200K at 80/20 in FFY 2025. Add design phase of $500K in STP50-200K at 80/20 in FFY 2025.
- H.016387 CORP DR & ENT DR INT IMPROVEMENTS: New Project. Add environmental phase of $50K in STP50-200K at 80/20 in FFY 2025. Add design phase of $500K in STP50-200K at 80/20 in FFY 2025.
May 19, 2025: An administrative modification has been issued to correct a typographical error in Version 5.0 (dated October 26, 2023), which incorrectly listed the Federal Fiscal Year (FFY) as 2024 for Amendment H.014802: LA 316 & LA 24 – Mill, Overlay, Grade Raising, HFST. The correct FFY for this amendment is 2023, as originally intended and approved. This modification updates the record to accurately reflect the July 27, 2023 amendment, which added the construction phase with the following funding: $3.58 million in STGEN, $1.535 million in HSIPPEN (100%), and $600,000 in PROTECT (80/20 split), all programmed in FFY 2023. The correction brings the record into alignment with Version 4.1 (dated July 27, 2023), which reflects the original LADOTD request and the appropriate funding year. It is important to note that a subsequent amendment dated April 24, 2025, revised the construction phases to FFY 2025.
- May 29, 2025: Amended H.015654 City of Thibodaux Ped Improvements to remove feasibility phase of $100,000 of STP 50-200k at 80/20 in FFY 2023.
- June 20, 2025: Administrative Modification replacing placeholder for Terrebonne Parish Transit (Good Earth Transit) 2025 Program of Projects with updated figures.
- July 14, 2025: Administrative Modification to include Louisiana US DOT-FHWA IIJA Competitive Projects Summary as of July 2025 which includes the following four projects:
- Bridge Investment Program (BIP): Replacement of Old LA 182 over Lafourche Bayou Planning: the feasibility planning study to determine potential alternatives to replace a bridge in Lafourche Parish.
- Rebuilding American Infrastructure with Sustainability and Equity (RAISE): Resiliency Plan for LA Highway 1: this project will fund the development of a comprehensive resiliency plan forapproximately 7-miles of LA Hwy 1 along the Gulf of Mexico from Port Fourchon to the parish border at Thunder Bayou. The plan will consider risk management through traditional andnature-based solutions, flood protection measures, evacuation route planning, climate change predictions, as well as conduct stakeholder and public outreach.
- Valentine Pontoon Bridge Replacement: The project will replace the existing dilapidated Valentine Pontoon Bridge over Bayou Lafourche on State Highway 1 and 308 between Lockport and Larose with a more modernized pontoon bridge.
- Safe Streets and Roads for All (SS4A): Develop Safety Action Plan for the Assumption, Lafourche & Terrebonne Parishes, Louisiana: The award will be used by the South Central Planning and Development Commission to develop a comprehensive safety action plan.
- September 11, 2025: Administrative modifications to the following projects:
- H.013340 VALHI BOULEVARD, MULTI-USE TRAIL PHASE 1: Administrative Modification to move Construction phase to FFY 2026.
- H.016386 LA 311:SAVANNE INTERSECTION IMPROVEMENTS: Modification to move Environmental phase to FFY 2026.
- H.016386 LA 311:SAVANNE INTERSECTION IMPROVEMENTS: Administrative Modification to move Design phase to FFY 2026.
- H.016387 CORP DR & ENT DR INT IMPROVEMENTS: Administrative Modification to move Environmental phase to FFY 2026.
- H.016387 CORP DR & ENT DR INT IMPROVEMENTS: Administrative Modification to move Design phase to FFY 2026.
- H.016206 TIGER DRIVE: TALBOT AVE – LA 1: Administrative modification to revise TIP project names to align with LADOTD’s system.
- H.016198 CANAL BLVD: JACKSON STREET TO LA 1: Administrative modification to revise TIP project names to align with LADOTD’s system.
- H.013340 VALHI BLVD, MULTI-USE TRAIL, PHASE 1: Administrative modification to revise TIP project names to align with LADOTD’s system.
- October 23, 2025: The Houma-Thibodaux MPO adopted Louisiana’s five Highway Safety Improvement Plan (HSIP) Safety Performance Measures establishing a 1% target reduction across the following areas:
- 1% annual reduction in fatalities from a 2024 baseline of 46 to a target of 45 in 2026.
- 1% annual reduction in serious injuries from a 2024 baseline of 63 to a target of 62 in 2026.
- 1% annual reduction in fatality rate from a 2024 baseline of 2.441 to a target of 2.393 in 2026.
- 1% annual reduction in serious injury rate from a 2024 baseline of 3.344 to a target of 3.277 in 2026.
- 1% annual reduction in non-motorized fatalities and serious injuries from a 2024 baseline of 18 to a target of 17 in 2026.
- Additionally, the following projects were amended:
- H.011962 LA 1: CO CANAL MB REHAB (LOCKPORT) (HBI): Amended to remove Construction phase of $20M of STPFLEX at 80/20 in FFY 2026 (Phase is moving outside the current TIP/STIP years to FFY 2030
- H.013940 LA 648 & ACADIA ROAD INTERSECTION IMPROV: Amended to remove Design phase from FFY 2023 (the locals are using 100% Local funds for the Design Phase); ROW and Environmental phases moved to FFY 2026; Construction phase moved to FFY 2028. Amended to move ROW phase to FFY 2026 and Construction phase to FFY 2028.
- H.012859 CIVIC CENTER BLVD AT VALHI BLVD: Amended to move ROW phase to FFY 2026 and Construction phase to FFY 2027.
- H.016383 LAFOURCHE SCHOOL ZONES CROSSING UPGRADES: Amended to move Design phase to FFY 2026 and Construction phase to FFY 2027.
- H.015654 CITY OF THIBODAUX PED IMPROVEMENTS: Amended to move Design phase to FFY 2026 and Construction phase to FFY 2027.
- H.013453 BAYOU BLUE (LA 316) SIDEWALKS: Amended to move ROW phase to FFY 2026 and Construction phase to FFY 2027.
- H.016198 CANAL BLVD. OVERLAY: JACKSON STREET TO LA 1: Amended to move Design phase to FFY 2026 and Construction phase to FFY 2027.
- H.016206 TIGER DRIVE OVERLAY: TALBOT AVENUE TO LA 1: Amended to move Design phase to FFY 2026 and Construction phase to FFY 2027.
- H.016199 LA315: FALGOUT CANAL MB SUB CABLE RH(HBI): Amended to add Project and Construction phase of $450K in FBROFF at 80/20 in FFY 2026.
January 22, 2026: Amended H.016198 CANAL BLVD: JACKSON STREET TO LA 1: Add Project and Design (Engineering) phase at $147K of STP50-200K at 80/20 in FFY 2026. Amended H.016206 TIGER DRIVE: TALBOT AVE – LA 1: Add Project and Design (Engineering) phase at $109K of STP50-200K at 80/20 in FFY 2026.
- March 03, 2026: Administrative Modification to change Construction phase from $450K in FBROFF at 80/20 in FFY 2026 to $800K of FBROFF at 80/20 in FFY 2026.